Splash Pad re-work

If anyone has been by Collins Park in the last week likely noticed some changes with the Splash Pad.  We had an unfortunate setback that required cutting out and removing the small Toddler area of the Splash pad.  As of Saturday June 10, the concrete is removed and we can move forward. We hope to have the area re-poured in the next week or two.  Check back to www.sglions.org for updates and an Opening Date.

On the positive side of things, we have started to install the brick walkway with the donor bricks.  We still have work to do but it’s coming along nicely.  You can still make a donation to get an engraved brick, Buy-a-Brick Campaign.  Any donations we receive over our goal will go towards renovating the nearby bathrooms and installing a new water fountain.  We currently have $78k of the $80k needed.