Splash Pad update May 6

Several Volunteers and SG Lions members (John H, Mark C, Ankit K, Eric B, Doug S, and Mark S) came out May 6 to help build the small shed to enclose the Splash Pad equipment. We got the frame up; the sheathing and roof will follow.

The Splash Pad plumbing and rebar are being installed. The concrete is expected to be poured next week. We still have picnic tables, landscaping and a walkway to complete.  The Grand Opening is tentatively set for June 3. Watch SGLions.org for updates.

Donations have been steadily increasing the past 2 weeks. Donors can receive personalized engraved bricks that will be installed at the Splash Pad. You can donate here.  Any extra fundraising will go towards renovating the nearby bathroom facility.