Collins Park Pavilion update

Construction has begun on the Collins Park Pavilion.  Volunteers from the Lions and GE along with Park employees have been busy building the Pavilion.  You can follow our progress below.

November 1 – Concrete slab poured by Adirondack Landscaping.  The guys did a great job.  Pavilion signs to be installed soon.  The Village will be running electricity to the pavilion for lights.

pavilion floor 2 pavilion floor 3 Pavilion floor 1

October 5 – Completed shingle roof.  Weather held off just long enough to finish in one day.  Installed kiosk which will display donors and volunteers.

PavilionRoof

pavilionKiosk

September 19 – Finished installing remaining roof boards.  Edges to be sawed off clean and a few trim pieces to be added.  Shingle roof coming soon.

PavilionRoof3 PavilionRoof4

September 17 – Continue installing roof boards.  Lion’s District Governor Steve and 1st Vice District Governor Marianne came to help out to help.  Roof is nearing completion.

Pavilion_DGSteve

PavilionRoof3PavilionRoof2

 

September 10 – Half of roof boards installed

PavilionRoof

August 24 – Roof arches installed on posts.  Arches weigh 850 pounds each.

Pavilion arches

 

August 19 – Set posts in concrete

SetPosts

August 10 – Start construction.  Sealed lumbered and prepared site. Unfortunately discovered 4 feet of buried concrete (old Scotia bridge from 1960’s) only 12inches under ground.  Park workers used heavy equipment to jack hammer through it.

SitePrep

This entry was posted in Collins Park Pavillion Project. Bookmark the permalink.

One Response to Collins Park Pavilion update

  1. Dot Brooks says:

    Wonderful looking great.

Comments are closed.